Who We Are
Onterris is a global environmental solutions company partnering with organizations to solve complex challenges where environmental pressures, regulatory expectations and operational risks intersect.
Sectors
Access deep environmental expertise tailored to your industry, with solutions built for real-world conditions.
Solutions
Prepare for escalating environmental risks with expert solutions designed to perform under pressure.
Our Thinking
Explore briefs, perspectives and articles that turn insight into action. Discover thought leadership that informs decisions and drives impact. See the ideas shaping environmental solutions and guiding your next move.
Cuture & Careers
Where brilliant people come together to turn environmental science into real-world progress for communities, industry and the planet.

Decommissioning a Legacy Textile Site With Reliable PFAS Wastewater Treatment

Reliable commissioning and remote support maintained steady treatment performance in complex lagoon water as the site progressed toward closure

Person collecting a water sample by hand from the edge of a lake or pond for environmental testing.

Highlights

100M

Gallons of per- and polyfluoroalkyl substances (PFAS) wastewater treated from on-site lagoons

3

Treatment steps using granular activated carbon (GAC), sand filtration and single-use ion exchange

<70 ppt

Perfluorooctanesulfonic acid (PFOS) and perfluorooctanoic acid (PFOA) achieved to meet state-mandated discharge levels

Closing a legacy lagoon system with defensible PFAS performance

A legacy textile manufacturing site in the southeastern United States produced coated textiles containing PFAS for water- and oil-repellency. Historical operations left approximately 100 million gallons of PFAS-impacted wastewater stored in a series of unlined on-site lagoons. With the site in decommissioning and remediation, the project team needed a practical path to treat lagoon water and discharge it to a nearby river while meeting a state-mandated threshold of below 70 parts per trillion (ppt) for PFOS and PFOA.

The work called for more than selecting a technology. It required a treatment strategy that could hold performance in the field, with clear verification through standardized PFAS testing and consistent operational control.


When water chemistry is complex, operations decides whether treatment holds

Lagoon water chemistry introduced immediate constraints. Total dissolved solids (TDS) and total suspended solids (TSS) were elevated, increasing the likelihood of fouling and limiting media life if solids management slipped. Biological activity in the lagoons added variability, influencing pretreatment needs and run stability. A remote site location tightened the margin for error on mobilization, startup and troubleshooting, especially when equipment adjustments required fast decisions.

Meeting an ultra-low discharge target under these conditions meant the solution had to protect the PFAS polishing step from upstream variability. The plan also needed an operating model that stayed tuned after commissioning, not just installed.


A treatment train built to protect ion exchange performance

Onterris worked alongside the client team to design and deploy a treatment train that prioritized pretreatment before PFAS removal. The system used GAC upstream to reduce co-contaminants that can compete for treatment capacity. A back-washable sand filter is used to remove suspended solids and stabilize influent quality before polishing.

With upstream variability controlled, the project applied single-use ion exchange (IX) resin as the primary PFAS removal technology. Ion exchange provided a strong affinity for PFAS at low concentrations while supporting a compact vessel footprint. Field teams then optimized flow and loading to maintain consistent treatment efficiency as lagoon conditions shifted. Verification relied on national standard PFAS testing protocols to confirm results and document defensible performance against the state discharge requirement.

PFAS treatment succeeds when the system runs like an operation, not a pilot. Tight commissioning, a clear sampling cadence and responsive remote support kept performance steady even as lagoon water conditions changed.
Onterris Operations Team Member

Results that supported discharge and a repeatable closure pathway

The treatment train achieved PFOS and PFOA levels below the state-mandated discharge limit of 70 ppt while treating approximately 100 million gallons of lagoon water. Pretreatment reduced operational pressure on the ion exchange step, supporting stable performance in high-solids water and predictable treatment outputs.

Work continues as part of the broader decommissioning effort, with the operating approach serving as a repeatable model for legacy industrial sites managing PFAS and other emerging contaminants. The project reinforces a practical takeaway for environmental managers and remediation leads: reliable outcomes come from pairing chemistry-driven design with disciplined commissioning, documented verification and sustained operational support.

Explore Related Content

Turning Methane Data into Better Operational and Business Decisions

Using defensible methane data to prioritize action, improve performance and demonstrate value

California El Niño: Regulatory Guidance for Emergency Stream and Channel Work

Prepare for California El Niño impacts with guidance on emergency stream and channel work, regulatory coordination, documentation and response planning.

Rebuilding Highway 8 for a Changing River

See how Onterris helped rebuild Highway 8 along the Nicola River with climate-resilient bridge design, hydrotechnical engineering and habitat enhancements.

California SB 1137: Why Early Planning is Crucial for Oil and Gas Operators

Learn how California oil and gas operators can prepare for SB 1137 with early sampling, air dispersion modeling, EDS planning and a defensible LDRP.

Your Bottling Plant Measures Almost Everything. Why Not CO2 Loss?

Tracking carbon dioxide (CO₂) loss helps plants reduce emissions, prioritize repairs and protect margins

CERCLA Liability Exemptions for Brownfield Buyers

Learn which CERCLA liability exemptions and defenses may apply to brownfield owners, and why due diligence, AAI and documentation still matter.

When Landfills Run Hot: Why Leachate Strategy Matters

Learn how elevated temperature landfills can change leachate chemistry, treatment needs and costs and why early characterization and contingency planning matter.

Ontario O. Reg. 406/19: 2027 Excess Soil Rules

Ontario’s excess soil landfill restriction takes effect Jan. 1, 2027. Learn how O. Reg. 406/19 affects reuse planning, QP support and project schedules.

Building Environmental Certainty Before Shovels Hit the Ground

Early environmental insight helps project teams manage compliance risk, use resources more efficiently and build greater cost and schedule certainty into project delivery

Marcellus Gas: Environmental Data & Market Access

Explore how Marcellus gas operators can connect methane monitoring, environmental data and operations to build buyer confidence and support market access.