Australia’s pipeline of proposed data centre capacity is more than ten times its current operational capacity. As of 31 March 2026, 1.5 GW of capacity was operational, 3.3 GW was committed or under construction and a further 16.8 GW sat in early-stage projects. Data Centres Australia’s April 2026 forecast says these early-stage projects have not yet secured all the land, power and permits they need and “may or may not eventuate”.
In a speculative development pipeline, sites with known ground conditions and agreed management controls offer a distinct advantage. Policy in many states favours locating data centres on industrial and brownfield land, where contamination can drive cost, program and long-term liability.
Brownfield land will not suit every project. It is still worth considering during site selection, provided developers know what management or remediation a site needs, how long it will take, what it will cost and which liabilities remain. Data centres also have a risk profile that differs from other commercial and industrial uses. Contamination assessed against that profile can require less remediation than generic criteria suggest.
Policy is steering data centres towards industrial land
The NSW Data Centre Guidelines (August 2026) report “fewer complexities when data centres locate in brownfield sites with energy and water infrastructure capacity”. The Guidelines set six principles for data centre projects, from environmental and efficiency standards to community infrastructure and skills training. For projects that address these principles, the Department of Planning, Housing and Infrastructure commits to issuing the Secretary’s Environmental Assessment Requirements (SEARs) within two months. It also commits to assessing applications within 75 days. The contamination status of a site is usually understood from existing information gathered during due diligence. Fewer sites will have been assessed for how the contamination is best managed or built into a risk-based solution for the development. Where the site-specific strategy is still outstanding when the SEARs are issued, the investigation and planning needed to address them can absorb much of the time these commitments save.
Victoria’s Sustainable Data Centre Action Plan (September 2026) will prohibit data centres on residentially zoned land and set a 150 m buffer from homes. It has been reported that Queensland will take data centre assessment from councils.
None of the policies reviewed mentions contamination directly. Yet Data Centres Australia told a Senate inquiry that data centres “are confined to industrial and employment-zoned land, frequently brownfield sites”.
Contaminated does not mean unusable
Former industrial land can carry a broad range of contaminants, including petroleum hydrocarbons, chlorinated solvents, heavy metals, per- and polyfluoroalkyl substances (PFAS) and asbestos. These often come from imported fill, past operations and/or chemical storage. No single contaminant rules out redevelopment on its own. What matters is the risk each contaminant poses to future site users and the environment under the proposed land use.
Much of a data centre site sits under buildings or hardstand, access is controlled and the people on site are workers. These features limit direct contact with soil, the exposure pathway that drives most remediation for homes, schools and other sensitive land uses. Vapour intrusion and groundwater migration still need assessment. Data centres also differ from typical commercial and industrial buildings. Data halls are large spaces with ventilation and cooling designed around the equipment and staff spend limited time in them. Below ground, reconfiguration or installation of new services as part of the development can create potential pathways for vapour migration or intrusion that need to be managed. Considering the actual building design and operation when assessing risk from contamination avoids applying default commercial/industrial assumptions that may not fit the site.
The National Environment Protection (Assessment of Site Contamination) Measure 1999 , as amended 2013 (the NEPM), ties management or remediation to the current or proposed land use. Each state applies it through its own laws, so duties differ across borders, as the table below shows.
In NSW, Chapter 4 of State Environmental Planning Policy (Resilience and Hazards) 2021 requires contamination to be considered before consent. Victoria’s Planning Practice Note 30 (July 2021) adds requirements for sensitive uses such as homes, childcare centres and schools. A data centre is not one of them.
Recent NSW approvals show that contaminated sites can be developed as data centres where the contamination is appropriately managed. One data centre campus with asbestos in fill and PFAS in surface water was remediated, audited and approved. Another data centre has development consent on land with pesticides in fill and PFAS in groundwater. Its consent requires a site audit statement before the data centre can operate.
Environmental due diligence informs data centre site selection
Early investigation turns an unknown liability into a design input. It lets developers compare the cost and approval pathway of each management or remediation option.
Existing reports often give most of the picture, but they were prepared for a different purpose, land use or layout. Refining that picture for a data centre takes more sampling, reporting and engagement with the EPA or an environmental auditor. Minor data gaps can take weeks to close. Complex risk and remediation questions, including on- and off-site liability, can take months or more. That time is easiest to absorb before a site is committed.
Targeted remediation moves less soil
Remediation in Australia has often defaulted to excavation and off-site disposal for soil and pump-and-treat for groundwater. Both have a place. Used by default, excavation adds cost and embodied carbon, uses landfill space and shifts the problem elsewhere. Persistent contaminants such as PFAS often require treatment prior to disposal to minimise leaching from landfilled soil.
Clause 6(16) of the NEPM sets a preferred order of remediation options. Treatment on site comes first, followed by off-site treatment with the soil returned. Containment on site and removal to an approved facility are considered only where treatment is not practicable.
A good Conceptual Site Model (CSM) shows which soil poses a credible exposure risk or still acts as a source to groundwater and which only exceeds generic screening criteria. The resulting soil volume above generic screening criteria can be far greater than that based on site-specific target levels. Treating the source, where concentrations are highest and the footprint smallest, removes the contaminant mass that feeds groundwater.
The right treatment depends on the contaminant. Petroleum hydrocarbons biodegrade and can often be treated on site and reused. Metals in soil can be stabilised with binders and be placed beneath buildings and hardstand where the CSM and regulator support it. PFAS-affected soil can also be stabilised with sorbents and kept on site, though this is not yet routine. Regulators in different jurisdictions accept it to different degrees and its long-term effectiveness is still debated. Under the PFAS NEMP 3.1 , a proposal to keep stabilised PFAS soil on site should be backed by leachability testing, evidence of long-term performance and ongoing monitoring. Asbestos in fill can often stay under built form with cover or be contained with a management plan.
Chlorinated solvents, such as trichloroethene from former degreasing operations, often pose the greater risk beneath a building. They can sink below the water table, form long groundwater plumes and give off vapour that enters buildings through cracks and service penetrations. In-situ treatment of the source, with a vapour barrier or sub-slab venting in the building design, can manage that risk without mass excavation.
These choices cost least before the layout is fixed. Building footprints, basements, service trenches, piles and stormwater basins all change what can stay, move or be capped. Piles through contaminated fill can open a pathway to groundwater, so foundation design belongs in the remediation discussion.
Groundwater needs the same site-specific approach. Injected treatments suit well-defined source zones in moderately permeable ground, where receptors are far enough away to allow time for them to work. Depending on the contaminant, these include sorbents, oxidants or amendments that promote biodegradation. Where receptors are close, contaminant flux is high, the ground is heterogeneous or construction needs dewatering, groundwater must be captured and treated above ground.
Onterris has treated PFAS-affected groundwater at Katherine in the Northern Territory since 2017, starting with an interim plant delivered within four months of PFAS being identified. The full-scale 10 ML/d plant was commissioned in November 2023. Modular, containerised treatment systems developed by Onterris can also deploy quickly, which matters when dewatering sits on the construction program.
Plan for the environmental liability that remains
Where site data shows the residual risk is low, containment beneath buildings, hardstand or clean fill is often the most practical control for a data centre. Contamination left in place remains a liability and later works can disturb it, for example, where future workers may enter the subsurface to install or repair services. This risk is managed through a site management plan to notify future workers of the contaminant hazard and maintain separation controls.
Residual contamination can be recorded against the land, where it will be flagged to buyers and lenders. NSW consents can require a long-term environmental management plan to be noted on the planning certificate. Queensland sellers must disclose any register listing. Victorian sellers must tell a buyer whether EPA has been notified of contamination and what the notification contained. A buyer who finds notifiable contamination must notify EPA on taking control, unless a notification already covers it.
In Victoria, the duty to manage contaminated land can fall on a tenant, so an operator on a long lease can carry the duty for contamination it inherited. A baseline investigation before the lease starts separates that legacy from later contamination and sets the starting point for make-good terms.
Before committing to a brownfield site
Developers and investors should take these steps before buying or leasing:
- Establish the site history and search state registers (a listing, or its absence, proves nothing on its own)
- Investigate soil, groundwater and soil vapour, build a CSM and derive site-specific target levels
- Screen for threatened species habitat while the layout can still respond
- Test remediation and reuse options against the layout before it is fixed
- Plan groundwater management for dewatering and any plume control or treatment
- Price residual risk into the purchase price, lease terms, insurance and the investment case
An audit statement or approval does not remove liability. It records the condition of the site at a point in time. Regulators can still act on residual contamination or contamination found later and owners and occupiers keep their ongoing duties. In Victoria, audit statements reflect the condition of the site on the date they were issued. Western Australia allocates site classifications based on “the status of a site at a point in time”. In Queensland, remediated land comes off the Environmental Management Register only if it is suitable for any use.
Australia has industrial and contaminated land waiting for its next use. Data centres can be that use where developers know the site well enough to manage residual risk and remediate only what the use requires.